Bishkek CHPP Municipal Enterprise continues scheduled renovation and maintenance of the plant facilities in preparation for the autumn-winter period.
One of the key stages was the painting of the tallest pipe of the enterprise with a height of 300 meters.
The work was carried out by a specialized contractor with the involvement of industrial climbers, welders and electrical climbers, as well as using modern paint and varnish materials resistant to high temperatures and atmospheric influences.
The updated coating will increase the service life of the structure, ensure its protection from corrosion and adverse weather conditions, and also give the facility a neater and more modern look. To date, the work has been completed by 80%.