Bishkek CHPP Municipal Enterprise is actively implementing a repair plan in preparation for the upcoming autumn-winter period.


During the campaign, a set of measures is being implemented to ensure reliable and uninterrupted operation of the plant during the heating season. In particular, specialists carry out major and routine repairs of equipment, prevention of boilers, turbines and auxiliary equipment.

Currently in operation: 3 boilers, 2 turbine units with cross-links.

Under repair: 7 boilers, 3 turbine units, units No. 3,4.


The work is carried out in accordance with the approved schedule and is under the constant supervision of the company's technical services.


The main goal of the repair campaign is to provide citizens with reliable energy supply during the upcoming heating season. The station staff is doing everything possible to ensure that heat and light are delivered to homes on time and without interruptions.