The Leninsky Akimat, together with the city services, conducted a bypass, inspection of the construction of the sidewalk and bike path on the segment of Sadyrbayev Street from A.Masaliev to Semetey Street.
Construction is being carried out by MP "Bishkekasfaltservice" in order to implement projects for the improvement of the city of Bishkek, creating comfortable conditions for citizens and the development of active recreation.
The sidewalk with a bike path is located on the south side of Sadyrbayev Street with a total length of 2.8 km. Currently, work is underway to prepare the foundation of the sidewalk and bike path, demolition (dismantling) of obstructing objects.
Construction work is planned to be completed by May 2023.