The head of the Leninsky district, Ruslanbek Tagaev, checked the progress of work on the construction of a new building of the family medicine center No. 1, located on Selsovetskaya Street in the residential area of Kyzyl-Asker. The new building is scheduled to be commissioned in July 2023.

During the tour, a representative of the contractor organization Nac Stroy LLC informed the head about the current situation around the construction of the FMC Building No. 1 and topical issues that require attention.

To date, the bricklaying of the first and ground floors has been completed in the building under construction, electricity has been provided. Bricklaying continues on the second and third floors. The new building is designed for 150 visits. Its total area is 1,402 m2. The building of the building provides ECG, ultrasound, doctors' offices, technical and utility rooms, sterilization rooms, bathrooms.

The constructed FMC building No. 1 will allow providing assistance in comfortable conditions to a larger number of residents of the Leninsky district.