The head of the Leninsky district, Nurlanbek Tagaev, inspected the progress of the construction of the sewer collector d-1000mm on the segment of Asanaliev Street from Krasnaya to L. Tolstoy.
The construction of the sewer collector began in September 2022. The total length is 11 kilometers. It will allow connecting residents of the southern and western parts of Bishkek to the new drainage system. Construction work on this site is planned to be completed by the end of March 2023.
The work is carried out within the framework of the project "Rehabilitation of water supply and sewerage of Bishkek - phase II" through the PОМ "Bishkekvodokanal".
At the end of the field meeting, the head of the district instructed the responsible employees for rehabilitation and reconstruction to strengthen quality control and oblige contractors to perform all work on time.