The city continues to work. In order to provide uninterrupted heat to the townspeople next winter, the capital's mayor's office has already begun preparations for the heating season 2021-2022.
The communal enterprise "Bishkekteploenergo" during the inter-heating period will repair its boiler houses and heating networks in accordance with the plan of measures to prepare for the next heating season.
The repair of boilers, boiler-auxiliary equipment (smoke exhausters, fans, heat exchangers, pumps, chemical water treatment equipment, electrical equipment, gas equipment, instrumentation) is provided.
2.5 km of worn-out heating networks will be replaced, shut-off valves at heating networks and boiler houses will be repaired. In addition, it is planned to renovate boiler houses.
It is also planned to announce a tender for the purchase of local coal in the amount of 3.6 thousand tons.
In general, about 30 million soms are provided for construction work and preparation, funds will be allocated from the city budget.