In the capital, work continues to increase the capacity of schools and kindergartens.
With the onset of warm weather, the construction of a new educational building of school No. 72 on Kurchatov Street in the Jal microdistrict was resumed.
The building of the extension for 225 student places has already been erected, finishing work is now underway. Construction is carried out by the company "Monolit-Stroy" for 37 million 176 thousand 436 soms. The funds were allocated from an anti-corruption deposit account.
In turn, the capital construction department of the capital city hall announces a tender for the design and survey work of the transition gallery, which will connect the old and new school buildings.
The works are planned according to the title list of construction projects for 2021 under the item "Capital investments". The estimated cost of the design work was 235 thousand 19 soms, the funds are provided in the city budget.
Dear participants! Detailed information of the competition will be published today on the public procurement portal: www.zakupki.gov.kg